Fuselage

Fuselage Kit Order

August 1, 2015  Placed kit order
September 30, 2015  Fuselage kit received!

Firewall

September 27, 2016  Organized firewall parts
September 29, 2016  Fabricated F-601J angle
October 1, 2016  Match drilled firewall components
October 5, 2016  Dimpled firewall
October 6, 2016  Countersunk firewall stiffeners
October 18, 2016  Finished preparing stiffeners
October 22, 2016  Primed stiffeners
October 24, 2016  Started riveting stiffeners to firewall
November 13, 2016  Continued riveting firewall
November 27, 2016  Finished riveting firewall!

Bulkheads

October 20, 2016  Drilled rudder cable holes in aft bulkheads
December 3, 2016  Drilled holes in center section
December 5, 2016  Cut excess material from control brackets
December 18, 2016  Match drilled control brackets to wing box
December 29, 2016  Installed nutplates on center section
December 30, 2016 Cut center section brackets, F-605C doublers, and F-705B doubler
January 1, 2017  Fabricated tie-down bar, F-711C doublers, and F-705H spacer
January 2, 2017  Fabricated F-729C
January 7, 2017  Worked on F-705 bulkhead and F-711C bars
January 8, 2017  Modified F-711 bulkheads
January 9, 2017  Cut F-710B stiffener
January 11, 2017  Cut F-711 stiffener, drilled holes in F-708 bulkhead
January 14, 2017  Finished prepping F710, F711, and F712 bulkheads
January 15, 2017 Primed aft bulkheads
January 16, 2017  Drilled the F-728 stiffener
January 18, 2017  Drilled the F-729 stiffener
January 19, 2017 Assembled F706, F707, F711, and F712 bulkheads
February 4, 2017  Miscellaneous center section work **needs work**
February 8, 2017  F-706 bulkhead preparation
February 11, 2017 F-706 bulkhead assembly
March 23, 2017  Installed brackets to F-704 bulkhead
March 24, 2017  Finished F-704, Continued working on F-705
March 29, 2017  Cut the F-634 seat belt anchor flanges
April 1, 2017  Fabricated F-705G angles
April 3, 2017  Fabricated F-705K angle, Drilled one F-705L shim
April 4, 2017  Fabricated F-705J angle
April 10, 2017  Drilled F-705J angles to F-705F channel
April 15, 2017  Miscellaneous prep work on the F-705 bulkhead
April 17, 2017  Riveted F-705 bulkhead
April 26, 2017  Fabricated wing box spacers
May 25, 2017  Cut new F-605C bars, riveted F-705K to F-705 bulkhead
May 28, 2017  Riveted F-605C bars to F-705 bulkhead, riveted F-704G bars

Longerons

January 3, 2017  Cut J-stiffeners
January 22, 2017 Modified end of 1 stiffener
January 23, 2017  Modified ends of 2 stiffeners
January 26, 2017  Finished first 4 stiffeners, marked centerlines
June 11, 2017  Cut longerons
July 1, 2017  Started main bend on longerons
July 8, 2017  Finished main bend on longerons
July 9, 2017  Applied downward bend and twist to longerons
September 16, 2017  Cut new F-XXXA stiffener

Aft Fuselage 

January 19, 2017  Started assembly of the aft fuselage
January 28, 2017  Clecoed side skins and aft bulkheads
February 15, 2017  Installed F-706 bulkhead, worked on F-711 issues
February 25, 2017  Drilled J-stiffeners to skins
February 26, 2017  Leveled out fuselage, drilled J-stiffeners
February 27, 2017  Disassembled fuselage, dimpled right aft skin
March 1, 2017  Dimpled bottom aft skin
March 4, 2017  Dimpled left aft skin
March 5, 2017  Primed aft fuselage skins
March 7, 2017  Riveted F-711 and F-712 bulkheads to F-779 bottom skin
March 11, 2017  Finished priming aft fuselage
March 12, 2017  Started riveting aft fuselage
April 8, 2017  Continued riveting aft fuselage

Center Fuselage

December 19, 2016  Modified inboard center fuselage ribs
February 28, 2017  Fabricated F-916C spacer
March 14, 2017  Cut excess material form F-716 seat ribs
March 15, 2017  Cut out access area on F-716 seat ribs, drilled step hole in F-725 baggage rib
April 6, 2017  Fluted and deburred center section ribs
April 17, 2017  Assembled center section, Cut F-623 corner ribs
April 19, 2017  Match drilled F-623 corner ribs
April 29, 2017  Match drilled and countersunk the center section
April 30, 2017  Cut F-623A attach straps
May 1, 2017  Started dimpling center section bottom skin
May 6, 2017  Center section prep work
May 7, 2017  Drill crotch strap brackets
May 9, 2017  Dimpled F-704 flange holes
May 14, 2017  Primed center section bottom skin and ribs
May 21, 2017  Primed baggage ribs
May 29, 2017  Started riveting the center section skeleton
June 10, 2017  Finished riveting the center section skeleton
June 13, 2017  Emailed Vans, drilled out incorrect rivets in F-704
June 17, 2017  Redrilled the aft crotch strap bracket
June 18, 2017  Continued working on the crotch strap brackets, Started riveting the center section skin
June 24, 2017  Continued riveting center section
July 15, 2017  Finished riveting center section
July 16, 2017  Match drilled floors, started working on outer seat ribs
July 18, 2017  Fluted outer seat ribs, cut first crotch belt slot
July 22, 2017  Drilled outer seat ribs, cut second crotch belt slot
July 23, 2017  Cut slots in longerons
July 26, 2017  Cleccoed aft section and center section together
August 2, 2017  Cut step holes in side skins, fluted and drilled armrests
August 5, 2017  Bent transition tabs on side skins
August 12, 2017  Drilled left longeron
August 14, 2017  Started drilling right longeron
August 16, 2017  Continued drilling right longeron
August 30, 2017  Cut and drilled the F-904L straps
February 27, 2018  Cut F-904J spacer

Forward Fuselage

September 2, 2017  Began fitting firewall
September 4, 2017  Fabricated F-713 forward stiffeners
October 20, 2017  Cut brake pedal stiffeners
October 23, 2017  Trimmed and match drilled brake pedal stiffeners
October 28, 2017  Continued drilling brake pedals
December 9, 2017  Drilled firewall to fuselage
December 12, 2017  Finished drilling firewall, cut F-713 stringers
December 20, 2017  Drilled F-695 gussets
December 23, 2017  Cut left landing gear hole
December 29, 2017  Cut left landing leg scallop in F-704
January 6, 2018  Cut right landing gear holes and scallop
January 7, 2018  Drilled F-713-L and F-719-L left forward stiffeners
January 9, 2018  Match drilled F-719-R and F-713-R right forward stiffeners
January 11, 2018  Trimmed forward stiffeners
January 13, 2018  Drilled left lower longeron to firewall
January 18, 2018  Drilled right lower longeron to firewall
January 31, 2018  Drilled right F-XXX stringer to side skin
February 1, 2018  Fabricated F-XXX brackets
February 3, 2018  Assembled rudder pedals, Drilled F-684-L gusset,
February 5, 2018  Fabricated F-684-R gusset
February 8, 2018  Drilled the master cylinder holes in pilot’s brake pedals
February 9, 2018  Cut the center rudder support
February 10, 2018  Drilled the master cylinder holes in the passenger’s brake pedals, fabricated F-719B Angle Clip
February 13, 2018  Drilled mounting holes in rudder mounting block
February 15, 2018  Drilled inner left floor stiffener
February 16, 2018  Drilled rudder mounting blocks to F-XXX
February 18, 2018  Match drilled inner right floor stiffener, modified F-6118 Rudder Brace
February 20, 2018  Drilled floor stiffeners to F-704, drilled rudder cable hole in F-724
February 25, 2018  Drilled the bottom/side center skins to the aft bottom/side skins
February 26, 2018  Misc forward fuselage work
February 27, 2018  Fabricated F-9804J spacers
February 28, 2018  Rolled side skin conical section, Drilled F-724 to upper longeron and bottom skin
March 1, 2018  Drilled mounting holes in F-6116 rudder brace
March 3, 2018  Drilled the lower longeron to the firewall bracket
March 8, 2018  Started match drilling fuselage
March 10, 2018  Finished match drilling fuselage
March 17, 2018  Started the installation of the left gear mount
April 7, 2018
April 28, 2018  Disassembled fuselage

Forward Fuselage Preparation and Assembly

March 26, 2018  Dimpled bottom skin
April 29, 2018  Countersunk and deburred floor stiffeners
April 30, 2018  Fabricated armrest stiffener
May 1, 2018  Countersunk the armrest stiffener
May 2, 2018  More part deburring
May 5, 2018  Started dimpling the side skins, more countersinking
May 7, 2018  Deburred piece-parts
May 12, 2018  Finished dimpling and deburring right side skin
May 13, 2018  Dimpled right skin
May 21, 2018  Countersunk longerons
May 23, 2018  Finished countersinking longerons, dimpled aft skins
May 25, 2018  Deburred left side skin
May 26, 2018  Added countersinks for nutplates, dimpled bottom skin
May 27, 2018  Applied Akzo primer to bottom skin, longerons, and outer seat ribs
May 28, 2018  Drilled static port lines, masked firewall, primed fuselage piece-parts
June 2, 2018  Primed side skins and smaller parts
June 4, 2018  Received interior from Classic Aero, riveted nutplates
June 8, 2018  Drilled and primed armrests
June 11, 2018  Revieted forward stiffeners, riveted armrests
June 16, 2018  Painted numerous parts
June 19, 2018  Misc fuselage prep work
June 23, 2018  Riveted side skin plates, painted F-705
June 24, 2018  Got the center section ready for assembly
June 25, 2018  Clecoed left side of fuselage.
June 30, 2018  Finished clecoing fuselage together
July 10, 2018  Prep work before side skin riveting
July 11, 2018  Sealed firewall to airframe
July 14, 2018  Riveted most of left side of airplane
July 15, 2018  Started riveting right side of fuselage
July 18, 2018  Installed rivets in aft section of fuselage
July 29, 2018  Continued riveting right side of fuselage
August 19, 2018  Cut shim for left lower longeron
August 25, 2018  More fuselage riveting
August 26, 2018  Set nearly all rivets on the left side of the fuselage
September 3, 2018  Continued riveting the fuselage
October 6, 2018  Finished riveting left side of fuselage
October 7, 2018  Finished riveting right side of fuselage, FLIPPED THE CANOE

Aft Deck and Top Skin

October 14, 2018  Drilled harness anchors
October 15, 2018  Located F-656 Gussets, drilled and deburred F-635 Bellcrank
October 16, 2018  Fabricated F-635C Spacers
October 20, 2018  Drilled F-656 Gussets, Primed misc small parts
October 23, 2018  Riveted F-635 Elevator Bellcrank, Started riveting F-656 Gussets
October 28, 2018  Started riveting F-728B Stiffener, Finished riveting F-656 Gussets
October 31, 2018  Cut 2X4s for sawhorses
November 3, 2018  Mounted fuselage on new sawhorse, Drilled F-695-R
November 5, 2018  Drilled F-757-T Gusset
November 8, 2018  Drilled F-695-L Gusset
December 9, 2018  Riveted aft fuselage
December 15, 2018  Drilled F-714 Aft Deck to fuselage
December 17, 2018  Drilled F-709 Bulkhead
December 18, 2018  Cut F-786A J-Stiffener
December 19, 2018  Drilled right J-Stiffener to fuselage
December 28, 2018   Back drilled left J-Stiffener, dimpled rear top skin, dimpled J-stiffener
December 29, 2018  Drilled F-707B Angle Clip
December 30, 2018  Prepped Top fusleage parts for priming, Drilled new F-705G Angle
January 19, 2019  Primed top fuselage parts
February 24, 2019  Misc riveting around the F-705 Bulkhead
June 28, 2020
July 13, 2023

Fuselage Cabin Area

October 18, 2017  Cut flanges of seatback braces
October 19, 2017  Cut lightening holes in seatback brace, started working on seatback stiffeners
October 26, 2017  Fabricated 2 right side seatback stiffeners
October 31, 2017  Drilled the right stiffener to the pilot’s seatback
November 1, 2017  Drilled 3 seatback stiffeners, Drilled right stiffener to pilot’s seat
November 6, 2017  Drilled the passenger seat stiffeners
November 11, 2017  Cut left center tunnel bracket
November 13, 2017  Cut the horizaontal seat stiffeners, added fillet to upper seat stiffeners
November 18, 2017  Drilled upper pilot’s seat hinge
November 28, 2017  Drilled bottom pilot’s seat hinge
December 3, 2017  Drilled top and bottom hinges to passenger’s seat
December 5, 2017  Drilled hinges to left seat bottom
March 12, 2018  Cut radii in F-652 Upper Baggage Closeout
March 13, 2018  Fabricated F-766B Flap Actuator Angle
March 16, 2018  Fabricated F-680 Flap Bearing Block
March 26, 2018  Fabricated F-6114B and F-6114C Wear Blocks
March 27, 2018  Cut square washers and side step mounting block
March 28, 2018  Fabricated the horizontal stabilizer spacers
March 30, 2018  Cut the square hole in the F-757-T Gusset
April 16, 2018  Cut the elevator pushrod, drilled the threaded rod ends
November 10, 2018  Countersunk top deck of longeron, Started installation the right step
November 12, 2018  Continued working on the installation of the right step
January 5, 2019  Drilled Upper and Lower Baggage Bulkheads to fuselage
January 13, 2019  Drilled nutplate holes through F-706 Bulkhead
January 16, 2019  Fabricated custom conduit routing brackets
January 19, 2019  Started riveting nut plates to F-706 Bulkhead
March 4, 2019  Drilled nutplate holes in F-751 and F-762 Baggage Bulkheads
March 9, 2019  Performed all prep work on left external step
March 13, 2019  Match drilled right conduit brackets
March 16, 2019  Installed right conduit brackets, installed custom F-724 spacers
March 19, 2019  Deburred baggage area components
April 4, 2019  Drilled left conduit brackets
April 6, 2019  Primed external steps, primed baggage floor and sides
April 20, 2019  Installed external steps
April 28, 2019  Installed reaction blocks for external steps
May 11, 2019  Moved canopy, finished baggage area prep work
May 18, 2019  Painted the baggage panels/floors, installed F-750R Aft Baggage Side Cover
May 21, 2019  Installed F-750L Aft Baggage Side Cover
May 25, 2019  Installed F-747-L Left Baggage Floor
May 31, 2019  Primed F-652 Upper Baggage Bulkhead and F-749 Forward Baggage Side Covers
June 1, 2019  Installed F-747-R Right Baggage Floor, Started installing F-742 Aft Seat Floors
June 6, 2019  Drilled seat hinges to seat floor
June 8, 2019  Primed interior components
June 12, 2019  Riveted seat hinges to seat floor
June 15, 2019  Riveted left seat bottom
August 30, 2019  Drilled crotch strap brackets to seat bottom
September 1, 2019  Match drilled F-741B center tunnel top plate
September 7, 2019  Modified F-983C Fuel Valve Housing
September 16, 2019  Drilled the fuel selector valve to the mounting plate
September 29, 2019  Drilled F-7110 Stick Boot Doublers to seat floors
October 19, 2019  Primed right seat parts, Started riveting the seat backs
October 25, 2019  Finished riveting right seat back
October 26, 2019  Riveted tunnel cover, Drilled center tunnel covers to fuselage
October 27, 2019  Match drilled right seat back
January 5, 2020  Riveted fuel pump cover, Drilled F-982D Baffle
January 12, 2020
January 14, 2020
January 24, 2020
January 25, 2020
January 28, 2020
February 8, 2020
February 9, 2020
April 5, 2020  Installed ELT mounting plate
April 11, 2020  Primed and assembled left seat
April 18, 2020  Painted interior parts, Misc fuselage work

Canopy Frame

April 2, 2018  Cut F-732D and F-732E brackets
April 26, 2018  Cut F-631D, F-732D, and F-631E
June 13, 2018  Drilled large hole in aft canopy channels
June 20, 2018  Fabricated F-631C Angles
February 24, 2020  Started assembling frame
March 7, 2020  Drilled inner and outer straps to bottom frame
March 12, 2020  More frame work
March 14, 2020  Match drilled frame
March 15, 2020  Countersinking canopy frame
March 17, 2020  Made closeout on canopy channel
March 28, 2020  Riveted aft side of canopy frame
March 29, 2020  Riveted forward side of canopy frame
October 25, 2020  Drilled “keeper rivet” holes in mounting brackets
December 5, 2020  Drilled roll bar mounting brackets to fuselage
December 16, 2020  Drilled F-732A Channel to roll bar

Front Deck 

April 5, 2018  Fabricated F-703C Angles
April 9, 2018  Fabricated F-721C Angles
May 30, 2018  Started cutting F-703B
June 6, 2018  Cut F-768 first F-768D Seal Support Angles
June 7, 2018  Cut second F-768D Seal Support Angle
April 15, 2020  Drilled F-697 Channel to sub-panel
June 21, 2020  Drilled Seal Support Angles, match drilled Fwd Fuse Channels
August 29, 2020  Prepped center sub panel
August 30, 2020  Assembled center sub panel
September 5, 2020  Match drilling forward deck
September 19, 2020  Drilled top skin to firewall flange
September 26, 2020  **UPDATE**
October 11, 2020  Match drilled front deck top skin
October 17, 2020  Assembled F-768B Subpanel Bulkheads and F-745 Ribs

Landing Gear and Fluid Lines

April 24, 2020  Routed main fuel line
April 25, 2020  Installed right gear mount
April 26, 2020  Installed left gear mount
July 4, 2020  Installed gear mount fasteners
July 26, 2020  Routed right vent tubing
August 1, 2020  Routed left vent tubing
August 8, 2020  Installed fuel valve-to-pump tube

Wing Mating 

Empennage Mounting

January 20, 2024
March 23, 2024
March 24, 2024
March 27, 2024
June 15, 2024

Misc Fuselage

May 22, 2018  Cut aft canopy deck
August 22, 2020  Drilled static ports, drilled fwd engine control bracket

Move this:

January 7, 2023
January 8, 2023
November 18, 2023